Cougar baseball wishes to thank these fine sponsors for their very gracious and extremely generous support of our program. We hope that you will take note of these fine supporters of our team by giving them your support as well.   |  Go Cougrrrrrs!
 


  
BASEBALL BOOSTER'S PROJECT NEARS COMPLETION
Long Awaited Cougar Baseball Facility Nears The Finish Line


The new Lakeville South facility is valued at $47,000 when completed.

The long awaited Cougar Baseball Boosters press box facility is in the final legs of completion. After over three years of planning and setbacks, and one year of building, the project is moving into the final phase. With the help of 30 very benevolent businesses the boosters have been blessed with invaluable and generous donations, as well as great support in bringing this much needed project to fruition for the Lakeville South baseball program.

Left to complete as the project winds down:

  • Finish first floor tile grouting
  • Press box interior ceiling trim work
  • Press box furniture

The project was to be finished in winter. A request was made by the school in January asking if all work could wait until the spring melt due to the plowing issues in opening the road. The alumni boosters were forced to abide by the school's wishes. The road to the project is not part of their normal duties and the school couldn't plow it. Unfortunately Spring is the start of the busy season for contractors, so this in effect caused major scheduling issues for the project's completion. The boosters have now had to patiently wait for contractor availability in a horrible economy. We are deeply sorry if this has been perceived as an inconvenience for those waiting to use the new facility. We sincerely hope that parents would understand. It is a volunteer effort of professionals and they are committed to giving the school the best possible work for free. The facility will open as soon as all work is completed to city and state health code.

This project was made entirely possible by volunteer contractors in a historic down economy. The boosters thank all of our wonderful donators and supporters for their tremendous help and partnership in this project. Thank you for sticking with us and for honoring your invaluable contributions, despite the economic hardship for all. These companies all have their hearts in the right place and should be forever recognized for their contribution to LSHS and the South baseball program.
 


DAY 56: MJ TRIMMING GETS PRESS BOX CLOSER
Mark Johnson Uses Trim Skills To Give Press High-End Upscale Look


A very classy high-end look for one of the finest press boxes in Minnesota.

The press box project moved one step closer to completion when Mark Johnson, one of the finest trim specialists in the Twin Cities metro, went to work early in a Saturday morning rain to add some designer trim to help get the facility one step closer to its finish. Completed was the window and door trim, as well as the baseboards, all of which look absolutely fabulous and really give the facility an extra high-end classy look. Mark donated his time and professional skill sets to the cause to help give South Cougar baseball one of the finest facilities in Minnesota baseball. If you are in need of trimwork, or any professional building needs, please give Mark a call and let him do some professional quality work for your home or business. Mark is used to working on some of the finest homes in the Twin Cities metro and comes highly recommended from many building professionals. Call Mark at MJ Trimming, 612-201-1263. You'll be glad you did.


Mark Johnson installs baseboard trim in press box


Mark Johnson works in a Saturday morning light rain to finish press box trim..


HOM FURNITURE DONATES PRESS BOX FURNITURE
Lakeville Store Joins Project With Leather Couch Donation For Coaches

The folks at HOM Furniture in Lakeville have signed on to the project with the generous donation of a very comfortable leather couch and end table to fill the spacious new 16x16 press box. This gives the coaches a great place to retreat to before and after games. The Cougars thank Kip Bruce and the wonderful crew at HOM Furniture for being a part of this important project for South Cougar baseball. If you are in the need of new furniture, see the folks at HOM Furniture for the best selection and great prices. Remember, there's no place like HOM. 952-898-7878.

Watch this space for pictures to come soon.


LAKEVILLE TROPHY DONATES ENGRAVING SERVICES
Commemorative Black Granite Plaque Is Laser Etched By Gordy Erickson


Gordy Erickson of Lakeville Trophy with commemorative plaque for project.

The Cougar Baseball Boosters wish to thank Gordy Erickson of Lakeville Trophy Company for offering his services in etching the commemorative polished black granite plaque for the side of the new concession stand and press box facility. The 30 lb slab of granite was laser etched at Lakeville Trophy and looks absolutely fabulous. The commemorative plaque will be affixed to the north side of the building, forever thanking all those who had a hand in providing this much needed facility for South baseball. Each and every business who donated generously to this facility is noted, as well as The 2005-2008 boosters who initiated the project. Special thanks to Gordy Erickson for doing such an outstanding job. Great work Gordy! For all of your trophy, plaque and award needs, see the wonderful folks at Lakeville Trophy Co., 21017 Heron Way, Suite 109 in Lakeville. Call Gordy at 952-469-3323.


AFFORDABLE GRANITE DONATES STONE FOR PLAQUE
Commemorative Sign Thanking Donators Will Be Polished Black Granite


Tess from Affordable Granite shows off the 30 lb slab of polished black granite.

The commemorative sign that will adorn the new baseball facility will be a beautiful polished black granite that will forever denote and thank the generous benefactors who have made this project possible. The great folks at Affordable Granite in Lakeville have agreed to donate the 30 pound slab of polished granite to be used for the exterior plaque. The Cougar alumni boosters thank Tess and everyone at Affordable Granite for pitching in to help out with the new sign. The granite slab will now be laser etched by Gordy Erickson at Lakeville Trophy. If you're in need of the absolute best in granite, please consider the folks at Affordable Granite, 17613 Cedar Avenue in Lakeville. Call 952-891-1000.


NEW FACILITY RECEIVES BEAUTIFUL CUSTOM SIGN
New Sign Will Commemorate The Beginning Of Cougar Baseball In 2006


Lakeville South AD Neil Strader and Dan Gust of ActionPlus Signs in Apple Valley.

One of the awaited new pieces for the baseball press box facility is the addition of a fabulous new sign to adorn the building and also commemorate the beginning of South Cougar Baseball and its first season in 2006. Dan Gust of ActionPlus Signs in Apple Valley has been kind enough to donate his time and services to produce a sign designed by the alumni baseball boosters which will hang on the North face of the press box and be visible to all who come to the field. Dan is an outstanding guy and was truly great to work with. He is another of the many fine outstanding businessman who support Lakeville South baseball and truly has his heart in the right place. Many thanks to Dan and the folks at ActionPlus Signs for the beautiful donation to the new facility. If you or your business is in need of professional banners, signs or vehicle lettering, please give the great people at ActionPlus Signs a call at 952-891-4444. They do top quality work!


Dan Gust of ActionPlus Signs in Apple Valley with friend Ruby.


New baseball sign designed by alumni baseball boosters.
 


DAY 55: PRESS BOX CARPETING INSTALLED
Hertaus Floors Come Through For South Cougar Baseball


The press box carpet looks absolutely great in cardinal red.

The press box flooring is officially completed and looks beautiful. Ron Hertaus of Hertaus Floors stopped in bright and early on Thursday morning and did the entire floor on his own. The floor was covered in a durable indoor-outdoor carpet in cardinal red with flecks of black so as to hold up better and not show dirt. The carpet also adds an acoustic dampening to the room to alleviate echo and give it a much fuller sound for announcing and for the occasional radio broadcasts that will take place there. The Cougar alumni boosters thank Ron and Lisa Hertaus very much for their wonderful contribution to our project. If you are in need of carpet for your home or business, please give the folks at Hertaus Floors a call for great prices and the best professional installation. Call 952-469-5123. Thank you Hertaus Floors!


Ron Hertaus of Hertaus Floors, downtown Lakeville and New Prague.
 


DAY 54: CONCESSION STAND TRIM IS COMPLETE
Boosters Go Above And Beyond To Help LSBA With 4-Team Qualifier

Even though the alumni boosters have taken much undeserved heat from LSBA over a project that many of their members have been openly critical of, the alumni boosters worked their tails off, many nights past midnight, in order for the facility to be open ahead of schedule for a 4-team qualifier. The boosters did their utmost best to accommodate the event in the hopes of helping facilitate a successful fundraising effort for LSBA.

The new facility is now nearing completion after a major January setback. (see story above) It is hoped that with the proper care, the facility will serve Cougar baseball well for the next 40 to 50 years. Thank you to all who openly supported our efforts!


The northeast corner of the appliance wall.


The southeast corner of the appliance wall.


The east door showing the fancy trim molding installed by the alumni boosters.


The west window, highlighting the beautiful trim, cabinets and countertops.


The northwest corner, showing beautiful tile floor, cabinets and countertops..


OP/ED: A STORY FOR LSBA, "THE LITTLE RED HEN"
Summer Baseball Group Was Impatient, Unduly Critical of Project Delay

The alumni Cougar Baseball Boosters would be reticent, if not remiss in failing to set the record straight over unnecessary pitfalls incurred during their long planned four-year project to bring a much needed revenue mechanism to Cougar baseball.

Due to a request from the school to wait and finish the project in the spring, the slated January finish of the project was delayed. The alumni boosters had hoped to finish during the contractors slow season, however, issues in continually plowing the road to the project forced the school to request that all construction be delayed "until the spring melt." The boosters were not thrilled, but understood the school's plight and respectfully acquiesced to their request, even though spring would not only be the start of the baseball season, but also the contractors' busy season. The boosters understood the school's position, but sadly that same courtesy was not extended in kind to the alumni boosters, from others not directly affiliated with the school. Much pressure was unfairly levied to open the facility before contractors could even finish their work.

Even though they had nothing to do with offering the school this free new facility, LSBA, a summer baseball organization, was openly critical of the delay, even though it was no fault of the alumni boosters. Some in LSBA were highly critical of key figures who were responsible for the genesis and orchestration of the project. This was discouraging to many boosters who worked tirelessly in good faith (and poor health) to bring this needed revenue tool to South Cougar baseball.

Due to the impatience and unwarranted pressure of many in LSBA to open the facility before contractors could finish their work properly, the structure is now short some essential key amenities. The boosters are earnestly working hard to alleviate the issue and seek alternative solutions to get back these planned for, yet now missing, necessary components.

It is truly regretful that those delivering the criticism failed to understand the issues surrounding the project delay, and that they could not wait patiently for the final contracted work to be completed. The impatience of LSBA was without a doubt a negative influence and an undeniable hindrance to the project.

What many in LSBA failed to realize through their impassioned vitriol and behind the scenes rancor is that this has never been their project, nor will it ever be under their ownership. The fact is that all donations and the contracted professional help for this project were brokered by the alumni Cougar Baseball Boosters through web advertising on this website, which is paid solely by private money, none of which has ever come from the school, nor district 194, and certainly none ever from LSBA.

The alumni boosters have worked very diligently on their own, in many instances paying from their own pockets to finish as planned, all due to a key boosters Applebees pancake breakfast fundraiser that was myopically cancelled by others for no good reason, shorting the project $1,200. With their long range goal still in mind, the alumni boosters have persevered, despite these shortcomings, to finish what their group set out to do, which was to give Cougar baseball a valued revenue mechanism, as well as one of, if not the finest press box facilities in the state.

The alumni boosters thank those who have openly supported our efforts, giving our sincerest thanks to all of the Cougar baseball families from the classes of 2005 through 2009, all who helped support the group's fundraising quest to build the much needed facility. The boosters also want to thank District 194, particularly Stan Fredrickson, for the gratitude and understanding extended throughout this endeavor. It has been very much appreciated.

Last, but certainly not least, the alumni boosters are most indebted to the 31 kind-hearted businesses who all agreed to freely donate and help build this beautiful new facility, all during arguably the worst economy in recorded history. The boosters thank each of these wonderful businesses from the utmost bottom of our hearts. We greatly appreciate the outstanding support. South baseball is much better off as a result of their tremendous generosity. We sincerely thank all of you very much!



A lesson generally learned in grade school for most.

Unlike the story ending of the little red hen who got to keep the fruits of her labor all to herself, the alumni boosters fully intend to turn this facility over to LSHS and the new Al Iverson baseball program. We certainly do hope that those in LSBA who were staunchly voicing their cynicism, while not helping in the least, would learn from their unwarranted and unnecessary criticism, especially when it comes to altruistic efforts from others outside their summer baseball group. Egos aside, it's all about building a great Cougar baseball program and giving South players the absolute very best that we can afford.


DAY 53: LOWER RAILING FINISHED; PILLARS WRAPPED
Concession Stand Railing Is Complete And Stair Pillars Are Upgraded

Another step closer to completion. The lower concession stand railing has finally been built and is in place. Rather than wait for contractors to make it back to finish, the boosters have stepped up to finish portions of the project on their own. The lower railing serves one primary function, as a overly excessive door-stop. The winds often blow hard at the South baseball fields and pull quite hard on the door when it is open. A door return was deemed not acceptable as the wind would have literally pulled it from the door or severely damaged it as a result of the strong wind force. So a simple railing was built to act as a doorstop, while also adding an aesthetic quality and matching look with the existing stair railing.


A concession door railing was constructed to act as a door-stop in heavy wind.

The 6x6 support posts for the upper press box landing were not the best looking, with large chunks missing and gouges in them, so they were wrapped in cedar for a beautiful finished look that upgrades their appearance tremendously.


The 6x6 green treated pillars have been wrapped with a nice cedar casing.


DAY 52: SOUND SYSTEM INSTALLED IN PRESS BOX
PA System Amp Much More Powerful Than Previous System; Music Rocks

The sound system for the new facility is a definite upgrade from the old portable amp used for the first five years. A 150w per channel powered mixer has been installed that will give fans a better audio experience while attending games. The music is louder and can be heard everywhere in the ballpark. The PA setup will also be more robust as a result giving a loud and clear address system for Cougar games. 


With 150w per channel, the press box sound system is ready to rock.


DAY 51: INTERIOR PAINTING IS COMPLETED
Cougar Colors Provide Color Splash For Press Box / Concession Stand

With the painting crew pulling out after the school's request to delay the project during the winter, the boosters had to finish the job on their own. At long last that portion of the project is now  completed. The interior colors are cardinal red on the east and west walls, with the north and south walls being Vegas gold. The ceiling is also gold to give it the lighter color. The upper and lower floors need to be finished, as well as the fancy trim work for the baseboards, windows and doors. The boosters have had to be patient in waiting for the professionals to free up time to get back into the facility. With their work being voluntarily donated, the boosters understand the contractor's need to take care of paying business first in this historic down economy.


Concession stand painting is finished. The east and south walls are shown.


Press box interior painting is complete. The east and south walls are shown.


DAY 50: COUNTERTOP INSTALLATION IS FINISHED
Hoffman's Countertops Comes Through For Lakeville South Baseball


(L-R) Pat Thompson, Derek Pfannenstein and Andy McKinley.

The countertops are officially in and look beautiful. Jeff Hoffman and his crew stopped in on Wednesday for the installation work. They were quick and extremely efficient in getting the job done right, with professional craftsmanship. The first step was to pre-measure the walls the week before, using a state of the art laser to note every nook and cranny of the sheetrock. Then it was off to the shop for a custom cut using their computer aided cutting machine. On Wednesday it was time to install. The end result was a precision fit, matching any swales in the wall perfectly. Special thanks to Jeff and Julie Hoffman, Adam Edwards, Derek Pfannenstein, Pat Thompson and Andy McKinley for their outstanding contribution to this project. Absolutely beautiful work gang! If your family or your business is ever in need of custom countertops, the great folks at Hoffman's are the people to call for a professional install and a quality finish. Give them a call at 952-469-6616 for the best in quality countertops.


(L-R) Pat Thompson, Andy McKinley, and Jeff Hoffman discuss the installation.


(L-R) Pat Thompson, Derek Pfannenstein and Andy McKinley in the press box.


A look at the west interior wall and the three sided countertops.


A look at the south wheel chair window with the countertops.


A look at the north wall countertops.


A look at the top floor press box facility.
 


DAY 49: COUNTERTOP PREPARATION COMPLETE
Designed Cabinets Completes Framing For Countertop Installation


Bill Prior works on the framing structure in preparation for the countertops..

The project is on its final legs as Designed Cabinets was able to come in and finish off the countertop framing on Wednesday. Now the folks at Hoffman's Countertops will be able to have a support system to install the countertops on. The project should hopefully move along pretty quick now.


North and west wall framing is complete.

Special thanks to Jeff Baron for coming through with the support framing, as well as Jim Kettinger who built the framing. Thanks also to cabinet veteran Billy Prior for the installation work. Very much appreciated guys. A job well done!


South and west wall framing is complete.
 


DAY 48: APPLIANCES DELIVERED
Warners' Stellian
Keeps It Cold For Baseball


Warners' Stellian was one of the first to donate to the project when it began.

One of the first donations made to the boosters ended up being one of the last to be installed, as the appliances were finally delivered to the new baseball facility. Jeffrey Warner of Warners' Stellian was one of the first to buy into the project early on with a big heart for helping a worthwhile community endeavor. Warners' Stellian donated three major appliances to the new facility back in 2006, however setbacks in the project kept the facility from becoming a reality until ground was broken on April 29th, 2009.

Warners' Stellian went above and beyond the call of duty by actually donating some larger appliances than expected. The facility will have separate refrigerators, the larger refrigerator is for beverages and the smaller refrigerator is strictly for food product. The chest freezer is for storage of perishable items.

The alumni Cougar Baseball Boosters thank Mr. Warner and all the great people at Warners' Stellian. Their support means everything to our school and our baseball program. If you should ever need new kitchen appliances for your home, the place to go is Warners' Stellian in Apple Valley. Please consider giving them your support as a show of thanks for their help in supporting our children and our community. Call them at 952-891-4700. Thank you again Warners' Stellian!
 


DAY 47: LOWER WINDOW RAIN-GUARDS INSTALLED
Pro Fab Builds Extra Rain Protection For Lower Flip Up Windows

As a precaution against a hard driving rain, the folks at Pro Fab have designed a simple rain-guard for over the top of each lower flip-up window, to keep rain water from getting behind the window seal. The new rain-guards are made of sturdy aluminum and were powder-coated with a white finish to match the trim. The folks at Pro Fab also manufactured a special prop-up tool for help in opening the metal flip-up windows. Many thanks to Ben Stuber and Randy Slagel at Pro Fab for all the great work. Much appreciated guys.


Rain-guard above window hinges protect window seal against a driving rain.
 


DAY 46: CABINETRY FINISHED
Designed Cabinets Finishes Cabinet And Cupboard Installation


Designed Cabinets CEO Jeff Barum checks cabinet-top measurements.

The cabinetry has been completed for the new baseball facility and looks great. The cabinets are a deep cherry tone with gold accent trim and brushed metal hardware.

The alumni Cougar Baseball Boosters wish to extend our thanks to Jim Kettinger, Mike Spencer, Billy Prior and Justin Winsor from Designed Cabinets for their help in getting things installed. A special thanks to company owner Jeff Baron for his gracious donation for this much needed facility. We very much appreciate his tremendous support in this project.

If you're ever in need of new cabinetry, please think of the good folks at Designed Cabinets in Lakeville and help show our Cougar thanks for their generous support. (952-469-2700)


A view of the West interior wall with cabinetry installed by Designed Cabinets.


A view of the left side corner cupboard space.


A view of the right side corner cupboard space.


A view of the press box cabinetry. A countertop will extend from wall to wall.


Justin Winsor stands next to the sporty new "Designed Cabinets-mobile."


DAY 45: CABINETRY INSTALLATION BEGINS
Designed Cabinets Begins Install Of Cabinets And Cupboards

The cabinetry has arrived and is being installed by Designed Cabinets of Lakeville. Owner Jeff Baron has graciously donated the cabinetry as well as the labor for the installation. A special Cougar thanks to the great folks at Designed Cabinets for this wonderful donation.


Mike Spencer and Billy Prior of Designed Cabinets work on cupboards.


Mike Spencer and Billy Prior of Designed Cabinets.

The top corner cupboards have been installed as of today. The lower cabinets will be set later.
 


DAY 44: INTERIOR ELECTRICAL DEVICING INSTALLED
ColliSys Adds Lighting, Electrical Outlets And Switches


Keith Habeck works hard on his Saturday off to add electrical fixtures.

The good folks at ColliSys were back to handle the electrical devicing for the project, with ace electrician Keith Habeck doing some Saturday weekend work to add the interior electrical fixtures. The facility now has lighting, outlets and switches as the project nears its final stages. Special thanks to Mr. Habeck and Collins Electrical Systems (ColliSys) for the invaluable help and contribution to this much need project for Lakeville South baseball.


First floor lighting shines brightly.


Second floor lighting looking good.
 


DAY 43: PRESS BOX HANDRAILS COMPLETE
Mark Johnson Construction Handles Railing Issue

There was one exterior task yet to complete before the weather gets ugly, that of installing dual hand-rails for the press box stairway. Mark Johnson was kind enough to donate his time and effort to completing this safety issue to meet city code.


Mark Johnson of MJ Trimming Inc., finishes the remaining railing work.

The outside railing work completes the exterior schedule.


Mark Johnson builds lower railing support.
 


DAY 42: GROUT DEGLAZING AND CLEANUP
Booster Cleanup Night Finishes Off Floor Cleaning

The floor work was completed with a final deglazing to help clean up the tile and grout. With booster help, all extraneous drying glaze was cleaned up and the flooring was finished.


The floor looks much better after the tile deglazing and clean up.


This is what the floor looked like after being covered with grout.
 


DAY 41: GROUTING THE FLOOR TILE
Final Floor Grouting Completes New Tile Surface

The floor surface was completed after two days of grouting by Al and Mike Grazzini. A special epoxy grout was used to seal the flooring in place. With the floor now complete, final finish work can continue as crews try to finish before the snow flies.


Al Grazzini mixes up the special epoxy grout for the floor.


Grazzini & Son: Al and Mike work together to complete grouting of the tile.
 


DAY 40: GROUTING THE FLOOR TILE
Tile Gets Special Epoxy Grout Applied To Seal The Floor

The tile flooring received a needed application of special epoxy grout to fully finish the new floor. Instead of Grazzini Brothers it was more Grazzini and son as the duo worked hard to complete the flooring. Owner Al Grazzini and son Mike, a baseball team member, split the work up between two nights of effort.


Al Grazzini begins work on the grout.

The first floor gets new tile, courtesy of Grazzini Brothers.


Al and Mike Grazzini work on the grout for the floor.
 


DAY 39: STARTING THE FLOOR TILE
Grazzini Bros., Tile Setter Tom Harrington Lays Out The Floor


Tom Harrington starts in on the floor by building out from the corner.

The flooring for the lower level began with the addition of a new tile surface, courtesy of Grazzini Brothers. Al Grazzini and tile setter Tom Harrington marked the floor out and then the work began. Using hard square tiles in school colors gives the room a feel with Cougar spirit. The work began around 8am and was finished by noon. Thanks to Tom for working so quickly and for doing such a great job.


Tom Harrington begins setting the floor tile.
 


DAY 38: ADDING SOME COLOR, PAINTING BEGINS
Young Painting Service Begins Work On Interior Wall Color

The final phase of interior painting has begun as Young Painting applies a semi-gloss finish in school colors. The design will be Vegas gold on the north and south walls as well as the ceiling. The east and west walls will be painted in cardinal red. This theme will be the same for both the lower and upper floors.


Yong and Leanna Young begin work on the lower floor.


Yong and Leanna apply Vegas gold to the press box.
 


DAY 37: INTERIOR DRYWALL PRIMER IS FINISHED
Young Painting Service Handles Interior Painting

The interior drywall painting began on this rainy Saturday as Young's Painting Service of Lakeville stepped forward to donate their services in putting some color to the inside walls. The husband and wife team of Yong and Leanna Kim will be painting the interior with the school colors of cardinal red and Vegas gold. Yong Kim completed the sheetrock primer coat in preparation for the color application. The duo will return later this week to apply the first of two finish coats as the project begins to wind to a completion.


Yong Kim primes the lower floor interior.


The press box ceiling is the last painting for the day.
 


DAY 36: INTERIOR DRYWALL IS COMPLETE
Drywall And Plaster Gets Sanded For A Smooth Finish


Alan and Ariel Pacheco complete sanding of drywall plaster.

Ariel and Alan Pacheco were back once again Monday morning to complete the drywall portion of the project as the new plaster received a fine sanding for a smooth finish. The walls and ceiling are now ready to paint as the final phase begins. Thanks very much to Friedges Drywall for donating the materials and labor. Thanks to the Pacheco brothers for their efforts in the taping and plastering. Great work guys!
 


DAY 35: DRYWALL PLASTER AND TAPING CONTINUE
Pachecos Work On Sunday, Applying Second Coat Of Plaster To Interior


The Pachecos: Alan, Ariel Jr. and Ariel Sr. work hard to finish the drywall.

The Pacheco family was back at it again on Sunday as they worked hard to apply the final coat of plaster to the drywall. This diligent crew works very hard and does great work when it comes to giving the drywall a professional finish. They will be back at it once more on Monday morning as they sand any rough edges for a smooth finish in preparation for painting. Great work guys!


Ariel Jr., Alan and Ariel Sr. working on first floor drywall finish.
 


DAY 34: DRYWALL AND TAPING BEGIN
Friedges Drywall Donates Labor And Sheetrock For Booster Project

Interior work began on Friday with Friedges Drywall offering their services to finish the interior walls. Todd Friedges very graciously sent a two-man work crew as well as a generous donation of dry wall and taping experts to give the interior a finished look. The crew of Tyrone Friedges and Harry Breuer did an outstanding job of sheet-rocking the facility with a solid morning of work that saw both floors completed with the professional quality workmanship that Friedges Drywall is renowned for. If you're in need of the best drywall service at a great price, call the folks at Fridges Drywall at 952-461-3288.


Harry Breuer and Tyrone Friedges work on the first floor ceiling.

Once the sheetrock was in place, Friedges called in their crack drywall plaster and taping crew to seal up the seams for a smooth drywall finish. Thanks to the guys from Pacheco Drywall for their excellent work in putting the final finish on the interior. Excellent work guys!


Fernando, Ariel and Alan Pecheco work on the first floor.
 


DAY 33: WALL AND CEILING INSULATION INSTALLED
Emond Insulation Teams With Northstar Wholesale Insulation

The alumni baseball boosters were elated to receive the help of both Emond Insulation and also North Star Wholesale Insulation. Mark Emond was happy to donate the labor force as well as coordinate the insulation donation. A crackerjack work force consisting of Pat and Sam Emonds, both coincidentally South students, completed the interior insulation and vapor barrier in record time, graciously donating their labor on a free Saturday morning. This should hopefully earn both students some high marks with the school. Thanks guys for the very professional installation.

If you're ever in need of insulation and professional installation, call Mark Emond 469-5688, Emund Insulation and North Star insulation.


Pat and Sam Emond tackle the task of insulating


The second floor press box is insulated and sealed up, awaiting sheet rock.


DAY 32: THERMAX INSULATION IS COMPLETED
Floor Joists Are Insulated Between First And Second Floors

Another hurdle was covered on this Saturday afternoon of work as the city required Thermax insulation board was cut and installed along the perimeter of the first floor ceiling and second floor joists. This helps to reduce condensation, while keeping the exterior temps separated from the interior. Special thanks to alumni booster Pat Daniels for his help and advice regarding the proper installation.


DAY 31: AUDIO SYSTEM AND SPEAKERS INSTALLED
Facility Receives Sound System And Exterior Speakers

Today was the day that the sound system and speakers were installed and tested. Using outdoor speakers donated from the Lakeville Best Buy, the facility now has a working sound system to announce games and play music with. A SoundTech powered mixer with 150-watts per channel gives the facility a significant upgrade over the previous sound system. With two speakers mounted under the east and west soffits, the sound system not only delivers to the home and visitor sections, but carries nicely onto the field as well. Thanks to alumni Cougar Eric Watts for his help in the installation and testing of the new sound system.


DAY 30: EXTERIOR PAINTING IS COMPLETE
Booster Help Finishes Siding Paint Job

The exterior painting was completed after purchasing a fifth gallon of paint. With the painter now on vacation and his stairway ladder extension gone, it was time to improvise in order to reach the upper wall. Using an extension ladder and scaffolding from Tekton, a remedy was found. While a little shaky and tough to balance on, it worked well enough to complete the painting. The exterior work was finally finished. Time to work on the interior.


A precarious perch to finish the upper east side wall.


The exterior is finally done. A look at the west and south sides.


DAY 29: BUILDING FINALLY GETS PAINT JOB
House Call Painting Gives Facility A Quality Exterior Finish

The exterior painting finally began as John Pieri from Housecall Painting donated his time and skill in putting a finish on the building exterior. The boosters provided some additional painting help, along with some very expensive and durable paint. John provided his expertise and his sprayer to get the project done. He did a magnificent job. Unfortunately, the four gallons from the boosters only made it through 3 1/2 sides, leaving the upper wall over the east side stairway to finish the following day, when more paint could be bought. Thanks John for the outstanding work!

If you are in need of professional painting services, please do not hesitate to call John Pieri and Housecall Painters at 898-3800.


John Pieri gets started on the north side of the building.


Housecall painting comes to the rescue.


DAY 28: METAL FLIP-UP WINDOWS ARE INSTALLED
First Floor Metal Windows Offer Shade As Well As A Security Asset

The long awaited lower floor window coverings finally arrived as Pro-Fab delivered three beautiful custom made metal flip-up windows. Co-owner Ben Stuber and assistant Nate Wall did a remarkable job with the new coverings, which offer an awning when open, providing a sun shade and protection from rain , but also a valuable security asset when closed. Stuber earlier stated that if he was given some time, he would really deliver on the window closures, and he certainly did. With the windows coverings in place, work can now begin on the interior.

If you ever need custom metal fabrication work, call Ben Stuber and the great folks at Pro-Fab 469-8988.


Bent Stuber and Nate Wall install the flip-up window coverings.


The west and south sides of the building.


The east and south sides of the building.


DAY 27: WHITE TRIM GETS PAINTED
Doors And Windows Get White Accent Trim

Work has begun on the exterior painting, with the window and door trim beginning first. Using a durable white latex, the doors and windows were triple coated with a nice accent trim. The trim was done before the full siding to accommodate the installation of the lower window coverings. Once the exterior is finished the window trim can be touched up to cover any spray over. Special thanks to Shannon Watts for her help in getting the trim painted.


Painting of the press box window trim begins.


The south and east side of the building.


DAY 26: CHALKING OF BUILDING IS FINISHED
Siding, Windows And Doors Are Weather Sealed

A second day of chalking completed the exterior work needed to to finish before painting. All siding gaps were sealed, as well as any gaps around the doors and windows. The exterior is now ready to paint.


The chalking of siding, doors and windows is completed as Eric Watts looks on.


DAY 25: HURRICANE CLIPS INSTALLED, CHALK BEGUN
Roof Trusses Are Tied To Building With Hurricane Clips

Another day of work saw the completion of necessary interior hardware as the hurricane clips were added to tie down the truss rafters to the top sill plate. Eric Watts volunteered his afternoon to secure each truss in order to meet the city and state code.


Eric Watts hammers away as he installs the hurricane clips to meet code.

Work also began on the exterior chalking, sealing up the gaps between the siding and any cracks around the windows and doors.


DAY 24: PRESS BOX STAIRS COMPLETED
Stahl & Tekton Finish Major Exterior Work


The building exterior after day 24 work completed.

Tuesday saw the finish of the major exterior work by Stahl and Tekton. Dave Wosika went solo for the day, finishing as much as he could in the sweltering 92 degree heat to end the exterior work from Stahl and Tekton. Dave was able to finish the upper deck supports, the press box stairs and door flashing. Special thanks to Dave for all of his exhausting efforts in getting this work done, especially in the heat.


Dave Wosika works on step treads and risers for the press box stairway.

The alumni-boosters will use parent volunteers to complete the unfinished stair railings, and exterior chalking. Once those tasks are out of the way, the painting of the building can be started. The alumni-boosters will also add the interior hurricane clips to the truss rafters in order to meet the city requirements for the final interior framing inspection. After the city signs off on the framing, the interior insulation work can be completed in preparation for hanging of the dry-wall.


Dave Wosika works on flashing under the press box door.


DAY 23: SIDING AND SOFFIT COMPLETED
Siding Completed; Press Box Stairs Underway

On Monday the team of Dave Wosika and Jim Kaczmarczyk worked on completing the east soffit and siding. On a hot day that saw the temperature hit 91, the two Tekton carpenters began laying out the stair stringers for the steps leading to the press box. The stairway treads and risers were half complete by the end of the work day, leaving completion of the steps for the following day.


Dave Wosika and Jim Kaczmarczyk do exterior finish work on the building.


Dave Wosika and Jim Kaczmarczyk work on laying out the stairway.


The 2005-2008 alumni baseball boosters thank all of our wonderful donators and supporters for their invaluable and outstanding contribution to this much needed project.

 

 

Lakeville Life & Times
Businesses team up, build new press box at Lakeville South

Despite tough economy, contractors step to the plate
by Laura Adelmann
ThisWeek Newspapers

Despite a difficult economy, several businesses have stepped to the plate to help Lakeville South baseball with a project designed to keep players on the field well into the future.
(Read full story here)


THANKS TO BASEBALL BOOSTER SUPPORTERS
Project Could Not Have Materialized Without The Generosity of Many

This project started as a direct result of Cougar baseball families who supported the Cougar Baseball Boosters for the last few years of fundraising. Without their patronage at baseball booster events, this project could have never begun. We thank you for your long support of Cougar Baseball Booster events.

The money the boosters were able to raise gave them the initial start-up capital, but it still wasn't enough to build the wonderful facility that will be finished. It was through the generosity of corporate material donations, many actually from outside the community, that this project became a reality. We thank all of our valued donators for their most generous donations.

The final piece to the press box project came into place with the tremendous labor involvement that was offered to the boosters. A breakfast meeting with Scott Everson from Stahl Construction was the catalyst that spring-boarded the project into gear. The Stahl Corporate Giving Committee was then approached by Mr. Everson, whereupon the group felt the project to be a worthy cause that they could contribute to, helping out a local community where they have been involved for so many years. Stahl is responsible for a large number of very successful construction projects in the city, including the new Lakeville police station, as well as many of the fine schools, including our own Lakeville South high school. The baseball boosters thank Wayne Stahl, Scott Everson, Josh Gangestad, Clark Evans and Brenda Studt, as well as the entire staff at Stahl Construction for taking on this much needed project, one which will serve as a necessary field amenity, but also as an invaluable revenue mechanism for South baseball for many years to come. The concession stand / press box project is apparently one of the larger community giving projects ever taken on by this group. The baseball boosters, the school and ISD 194 sincerely appreciate the magnanimous effort put forth and the invaluable support from the folks at Stahl Construction. The families of South High School and the people of Lakeville can be proud to have such a generous group that is willing to give back so much to a community. We cannot even begin to express the depth of our gratitude to this outstanding company and good hearted group of people.

Tekton Construction Services, a division of Stahl Construction, provided the skilled labor force of carpenters to build the new facility. Their building expertise is directly responsible for the solid structure we now have. Very special thanks to Steve Mayfield and Tekton carpenters Dave Wosika, Joe Kelly, Mike Culbertson, Paul Botko, Jim Spicer, John Clare, Dave Goetzke, Perry Andrews, Craig Kasa and Jamie Graff for their extensive labor in erecting the new structure. Great job guys!

Pro-Build became another integral piece to the project. Manager Mike Bensen originally accepted the project and was willing to donate the expensive roof, but eventually was transferred before the project could begin. New manager Dan Lieser stepped in and was kind enough to not only continue that commitment, but upped the ante by helping with the building materials after Cemstone pulled out of the project. Mr. Lieser coordinated all the materials and their timely delivery during the project. This was a tremendous gesture on the part of Mr. Lieser, one which literally saved the project and for which the boosters are very much grateful for. Thanks to boom-truck drivers Aaron Zweber and Dan Borck for their assistance in getting materials to the site. Thanks also to Pro-Build architect Nicole Danzl from the Zimmerman office for her fine work in formalizing the booster design in blueprint form. Thank you all at Pro-Build.

Anchor Block became another highly valued contributor as they stepped in to offer the free concrete foundation blocks for the project, along with a generous donation of 40 bags of pre-mixed mortar. Every project starts from the bottom up and Anchor Block provided the solid foundation for which the boosters were able to build upon. The boosters sincerely appreciate the good folks at Anchor block for stepping in to the rescue with the much needed block and mortar. We thank Sandy Stoffel, Kevin Hegyi, Mark Severson and the management at Anchor Block for their valuable gift which became the solid base for this project.

Every foundation also has a start and in this case it meant the much needed trenching and excavating of the project in order to begin. John Friedges of Friedges Landscaping & Excavating was a big help in getting the project moving as quickly as it did by literally agreeing on one days notice to start the excavation sooner than expected to meet the masons busy schedule. Mr. Friedges graciously agreed to provide the free labor in getting the site prepared, actually doing the excavation himself on a rainy day. We thank John Friedges for his efforts, as well as Dale Green from sister company South Metro Rental, which provided the heavy equipment for the project. Great work from Friedges Landscaping & Excavation and South Metro Rental!

Once the trenching was completed, footings were needed to build the foundation upon. Apple Valley Ready-Mix stepped in at the last minute with a tremendous gesture to replace the concrete lost from competitor Cemstone, donating the much needed concrete for the footings as well as the slab flooring for the facility. The boosters wish to thank AVR president Peter Fischer for very kindly stepping in at the last minute and his invaluable offer of free concrete for the interior portion of the project. The boosters appreciate Mr. Fischer's outstanding support. Thanks also to Pete's fabulous delivery crew of Paul Bredehoft and Brian Runpza of Apple Valley Ready-Mix (AVR). Thanks very much guys for the great donation for the interior portion of the new structure.

One of the largest problems that held the project up for many months was finding a mason crew to handle the skilled level of craftsmanship to pour the concrete footings, lay the foundation block, pour the slab flooring and deal with the sidewalks. It took a real baseball supporter by the name of Terry Fredrickson from Viking Concrete & Masonry of Elko to step in and offer his services to help the boosters out, actually working on his weekend off just to get the project started. Terry has already put in many hours on the project. A super effort and most professional job well done, The boosters thank Terry & Brad Fredrickson, Matt Lyrenmann, Luther Schmidt, John Ricci, and Doug Swedin for their contribution to the project.

Another need for the new facility was a sidewalk to surround the building, filling in where the asphalt was cut out and finishing the exterior ground surface off. Aggregate Industries did their part to help by donating the concrete for the sidewalk. A lot of cement was needed for this project so the extra help from Aggregate Industries made the sizable concrete donation much easier to handle for the two companies helping with the much needed cement. They were able to help the masonry company out with a continual sidewalk pour so that the job could be finished on schedule. The boosters wish to thank Don Vry and Tom Ryan from the Eagan office of Aggregate Industries, where they handle ready-mix, concrete and quality aggregates. Thanks also to driver Brad Gust for the timely delivery. Thanks very much guys for helping to keep the project on schedule so the masons could finish with a one day pour. Much appreciated.

While the project had many setbacks, one major obstacle was the fact that the major electrical trunk for the South varsity field just happened to run through the project site, potentially forcing the boosters to seek yet another location. Manger Bret Young of ColliSys Electrical Systems came to the rescue by sending Keith Habeck, one of the nicest guys you'll ever meet, to help reroute the high power, pulling the transformer from the dugout wall and putting it on the new concession stand, thus saving the location for the project. Mr. Habeck also has worked on his weekends off in order to get this project going as quickly as possible. Habeck has recently been joined by another superb ColliSys wiring wiz, Scott Smith, in helping to finish up the needed electrical for the facility. These two have been a solid one-two punch in knocking this out as quickly as possible. The boosters wish to thank them both, as well as Mr. Bret Young of ColliSys for donating countless hours and costly materials to the facility. We appreciate Mr. Young for sending his A-team.

Another valuable asset to the project came from Pro-Fab Welding & Machine who agreed to make custom metal flip-up windows, much like the previous concession wagons used by the boosters. Not only would the flip-up windows provide an overhead awning for shade and rain protection, but more importantly they would provide secure protection against possible vandalism or break-ins, as opposed to using glass windows. The boosters thank Ben Stuber amd Randy Slagel for their valuable expertise in the custom design and manufacture of the much needed first floor concession stand windows.

This project did however need actual glass windows for the second-story press box facility. The boosters were fortunate enough to make the acquaintance of Jim and Rhonda Steffes from New Windows For America-Minnesota. This Shoreview company graciously agreed to provide the boosters the beautiful second floor press box windows for which we are extremely thankful for. This husband and wife team were also two very nice people to meet and deal with. We cannot thank them enough for being involved in a project outside of their own community, although they do offer the same quality windows to Lakeville homeowners should you ever be in the market for residential windows. Thank you Jim and Rhonda for the quality press box windows from New Windows For America - Minnesota.

Another need for the project was cabinetry for the concession stand. Local company Designed Cabinets was happy to offer their beautiful quality finished cabinets and professional services in providing the facility with some much needed storage. Thanks to owner Jeff Barum for this much appreciated offering of the cabinetry and storage. Mr. Barum has been given the leeway to furnish the space as best as possible per the design. Thanks also to former financial comptroller Adam VanGrinsven for bringing the project to the attention of Designed Cabinets and  getting the process started. The boosters thank Mr. Barum and Designed Cabinets for their professional expertise and wonderful donation. These quality cabinets will be a great addition to the new facility.

You certainly can't have cabinets without countertops so the good folks at Hoffman's Countertops and Cabinets have joined in the effort to outfit the facility with countertops for not only the lower concession stand, but also the upper press box as well. This donation from the folks at Hoffman's is greatly appreciated and will help in meeting the state health code for a non-porous countertop surface. We thank Jeff Hoffman for being so kind to help on the project and look forward to the professional custom built countertops for the new concession stand / press box. The boosters thank Mr. Hoffman and all the good folks at Hoffman's Countertops and Cabinets for their valued support.

Once the building is completed it needs specific amenities and appliances to become functional. A solid supporter from the very start, Jeffrey Warner, CEO and President of Warners' Stellian, made a magnificent donation of much needed appliances to fill the inside with. Mr. Warner was kind enough to donate a large refrigerator for soft drinks, another refrigerator for food items and a small chest freezer for storage of perishables. The boosters are elated with the support from Warners' Stellian and wish to sincerely thank them and Mr. Warner very much for their much appreciated contribution.

When it comes to the second floor press box, the boosters realized they needed a nice flooring surface to cover the particle board floor. Hertaus Floors of Lakeville didn't have to think twice when asked if they would be interested in helping out for the project. They said yes immediately to provide a flooring surface for the second-story press box area. The Cougar Baseball Boosters are thrilled to have the folks at Hertaus Floors provide their expertise in covering the press box area with a beautiful new floor surface. Thanks to Bill and Ron Hertaus for their nice gift and for their support of the concession stand and press box project. Thanks very much guys!

One of the last pieces to the puzzle is the final trim molding and MJ Trimming, Inc has agreed to put the finishing touches on the trim work for the project. Owner Mark Johnson has over twenty years of experience doing finish trim work. He has agreed to donate his time and efforts to helping finish the interior and exterior finishing aspects of the project. Mark also finished the stair railings as well as the lower concession door railing and door stop. The boosters thank Mark and the crew at MJ Trimming Inc for their expertise and their much valued support.

The good folks at the new Lakeville Best Buy have also helped out with a donation of outdoor speakers which will attach to the press box, as well as a new PA system for the press box facility. The new Lakeville Best Buy, located near I-35 and 185th street in the Timbercrest shopping center, continues to be a proud supporter of Cougar Baseball. Their contribution is greatly appreciated and certainly helps in the press box and also with music entertainment in-between innings. Special thanks to GM Alex Bartlett and also to Deborah McNulty from the Lakeville Best Buy for helping with the much needed new sound system.

The commercial locks for the concession stand and press box doors weren't cheap, but Ryan Hauser of the downtown Ace Hardware came to the rescue with the much needed Sclage door knobs and deadbolts. Ryan was also good enough to help with installation of the locks when we had problems. Now that's great service! Thanks to Ryan and the downtown Ace Hardware store for all of their help and support. Stop in and see them in their brand new store on main street in downtown Lakeville.

A most special component for the new baseball facility will be a beautiful new booster-designed sign that will adorn the North upper face of the press box. It will be visible to all who come to the field, as well as those traveling on 210th street. The sign commemorates the establishment of South Cougar Baseball in 2006. Dan Gust of ActionPlus Signs in Apple Valley really came through with a beautiful sign. He was able to take the booster artwork and then vectorize it for a larger image. The sign is a nice finishing touch to the facility and the boosters cannot thank Mr. Gust and the folks from ActionPlus Signs enough for this beautiful contribution.

A huge thank you also to the good folks from Elko Baseball who very generously contributed $1,000 towards the completion of the press box and concession stand project. Even with the myriad list of magnificent business supporters, there have still been sundry financial costs to to deal with in finishing the project, including the city building permit, along with other miscellaneous project expenses, one of which being a very necessary field watering tap for the varsity field. The Elko Baseball committee was approached for help and they eagerly chipped in with the financial donation, made out to Lakeville South high school. The boosters thank the Fredrickson family and the entire Elko Baseball committee for their generosity and wonderful support. Thank you Elko Baseball very much!

This much needed facility has been in the making for some time and the baseball boosters thank each and every one of these great companies for helping out, especially in such a bad economic downturn. These businesses have faithfully and most kind heartedly stayed with the boosters throughout this long process. We are deeply indebted. We cannot possibly say thank you enough, but we would like to urge the families of Cougar nation to show their support of these great companies in these tough times, should they ever be in need of any such materials or services.

Thanks also to the City of Lakeville for helping to make this process move forward as efficiently as possible. Thanks to Gene Abbott and Brad Sticha for their involvement. Posthumous thanks to Jay Rubash who was killed in a motorcycle accident during the course of this project. Our sincerest condolences to his family. Very special thanks to city inspector Dave Peterson for stepping in and kindly helping out with so many aspects of this project as it has come to fruition. Thanks so very much.

A special thank you also to ISD 194 member Stan Fredrickson for his wisdom and guidance throughout this process. Stan is the king of all fields for the Lakeville school district and we thank him for his passionate support.

Last but not least, thank you to the Cougar Baseball Boosters, the greater portion being alumni members whose kids have long left the school and baseball program, but still offered much help throughout the course of this altruistic and benevolent endeavor. Thanks to Joel Blaschko, Steve Clarke, Randy Sleeper, Jeff West, and especially Pat Daniels for all of their tireless and much appreciated efforts. You guys are the absolute best!

To everyone listed above...we literally couldn't have done this project without any of you. Thank you all very much!


OUR WONDERFUL DONATORS



THANKS TO LOCAL FOOD & COFFEE MERCHANTS

Construction Crews Very Much Appreciate Donated Food

Many thanks to four outstanding Cougar baseball supporters, Lakeville restaurants Green Mill, the new Buffalo Wild Wings and the Kenwood Avenue Starbucks Coffee. A special g'day mate to Burnsville's Outback Steakhouse as well. With so many laborers donating their time and efforts it was nice to be able to treat the crews over the weeks to some great food during the process. The construction workers were happy with the piping hot pizza from Green Mill Restaurant, the savory taste of barbecue chicken from the new Buffalo Wild Wings, as well as the half pound gourmet hamburgers from Outback Steakhouse. The early morning hours were also easier to handle with the great taste of Starbucks hot coffee.

Special thanks to Tim Kreiser of Green Mill Restaurant, Ken Kooyer of Starbucks, Jerry Eck of the new Buffalo Wild Wings and to Jamie Klug and Matt Sherrer from Outback Steakhouse of Burnsville. These gentlemen and their great companies have always been staunch supporters of Cougar baseball. It was a very nice thing to do from some big hearted area businesses. Please show your support for them whenever at all possible. Thank you very much guys!


DICK'S SANITATION HELPS CLEAN UP WORKSITE
Company Chips In With Dumpster To Help With Materials Clean-Up

The great folks at Dick's Sanitation came to the rescue with the use of a roll-off dumpster on Wednesday to help clean up the worksite debris. With a pile of existing asphalt that needed to be removed, Dick's was literally on the spot within minutes to help with the debris removal. Thanks to Troy Nielsen and driver Jim Creighton for the efficient and very speedy service!


Dick's Sanitation Inc., helps with the removal of site debris.


DAY 22: SIDING AND SOFFIT WORK NEARLY DONE
North Siding Complete; Soffits 99% Complete

Friday saw the completion of the north wall siding and soffit work. The team of Dave Wosika and Jamie Graff worked diligently on the remaining siding and leftover soffit work, along with some chalking of seams and corners. Tekton supervisor Steve Mayfield also stopped by to help lay out the rise and run for the stair stringers. The team has about 15 minutes work left on the east soffit and siding, so the remaining exterior work to be done will be the stairs to the new press box and chalking of the building.


Jamie Graff and Dave Wosika finish up the north wall siding.


Steve Mayfield lays out stair stringer with Dave Wosika.


Dave Wosika and Steve Mayfield position stair stringer.


The SE and NW corners of the concession stand (rotating picture).


DAY 21: MORE SIDING TO FINISH ON PRESS BOX
South And West Siding Is Completed, Upper North Half Is Only Side Left

The siding work continued on Friday as a small Tekton crew of Dave Wosika and Jamie Graff finished off trimming out the press box windows and worked more on the siding. The south side was completed as well as the west side. All that is left is the upper north side of the building. Once the siding is done, the gaps and outer windows will be chalked in preparation for paint. Left to complete after that is the north and east soffits and the press box stairs. The lower custom flip-up windows will be installed soon and then the interior work will begin. Once the sheetrock is completed, the cabinetry, countertops and flooring will be installed.


Jamie Graff and Dave Wosika work on the west side.


Dave Wosika and Jamie Graff work on siding the press box .


Siding nears completion of the press box facility.


DAY 20: SIDING WORK CONTINUES
Work Nears Completion On New South Press Box

Work continues on the South press box as the cement siding goes up. Stahl Construction and Tekton workers put in another day of work as the project progresses.


Stahl and Tekton employees Mark Ramsland, Dale Sonnichsen and Joe Kelly.

The siding on the east side is up to the soffit while the south side is up to the press box windows. The west and north sides should go much quicker now since the siding is past the windows and there are no more cutouts to deal with.


(L-R) Leroy Wagner, Mark Ramsland, Dale Sonnichsen and Joe Kelly.

Thanks to Stahl Construction supervisors Leroy Wagner and Mark Ramsland, project manager Dale Sonnichsen and Tekton carpenter Joe Kelly for their assistance. The baseball boosters are extremely thankful and forever indebted to these wonderful benefactors for their generosity and professional expertise.


The east and south siding is close to complete.


DAY 19: CONCRETE SIDEWALK IS FINALLY FINISHED
Viking Concrete & Masonry And Aggregate Industries Team Up For Pour


Matt Lyrenmann and Doug Swedin finish sidewalk prep before the pour.

Wednesday finally became concrete day, but after putting it off on Tuesday due to the threat of rain (which never came), you just had to know it was going to rain on Wednesday. It did. Just like washing and waxing your car. It seems like it always rains when you don't want it to. The guys at Viking Concrete & Masonry teamed up with the good folks from Aggregate Industries and the sidewalk pour was on. Terry Fredrickson, Doug Swedin and Matt Lyrenmann finished prepping the surrounding sidewalk area and awaited the very punctual 9:00 delivery of the concrete truck from Aggregate Industries Ready-Mix, Concrete & Quality Aggregates.


Terry Fredrickson, Matt Lyrenmann and Doug Swedin work the concrete.


Aggregate Industries comes in for the one day pour to finish the sidewalks.

Within a two hour period the sidewalks were done, but early in the afternoon the rain started to come. Terry Fredrickson was on the spot quickly with plastic sheeting and the freshly poured sidewalks were safe from any water damage. Most of the fresh concrete had already set up enough by that time so the danger was only from the long drop of overhead dripping from the roofline.


Terry Fredrickson inspects as Doug Swedin and Matt Lyrenmann finish.

The tarp was removed on Thursday and the sidewalks looked great. Thanks to Viking Concrete & Masonry and the folks at Aggregate Industries for getting the job done in one day's time.

Special thanks to Don Vry and Tom Ryan from the Eagan office for arranging the donation so quickly and thanks to driver Brad Gust for the timely delivery. The Tekton crew will be able to roll their heavy scaffolding around the building easily now and finish the exterior siding and soffit work without dragging the awkward scaffolding through piles of cumbersome sand. Work will continue on Saturday.


Finished sidewalks now surround the new structure.


DAY 18: ASPHALT CUT AND SIDEWALK IS PREPPED
Viking Concrete & Masonry Is Back To Do Sidewalk Prep

The Tuesday concrete pour was put off a day with the chance of rain in the forecast, but that didn't stop Terry Fredrickson from cutting the asphalt away and preparing the area around the concession stand / press box for the new sidewalk. Fredrickson worked the day getting ready for hopefully better weather conditions and a Wednesday pour from Aggregate Industries. A new sidewalk will surround the structure to help complete yet one more phase of the exterior portion of the project. Thanks to Terry and Viking Concrete & Masonry of Elko for getting the job done. Thanks also to Dale Green of South Metro Rental for kindly lending the asphalt blade to cut the surface with. Very much appreciated guys!


Terry Fredrickson cuts away at the asphalt to prep for the new sidewalk.


Jack hammering away to break up the cut out portion of the asphalt.
 


DAY 17: PRESS BOX LANDING ERECTED
Press Box Landing Is Built To Prep For Concrete Sidewalk Pour

Memorial Day was supposed to be a day off, but workers gamely volunteered to help get the site ready for a possible Tuesday concrete pour, by erecting the press box floor landing needed to be set in the lower sidewalk. Stahl employee Dave Wosika and Cougar Baseball Booster member Steve Clarke pitched in to help get the site ready by working on the holiday. The press box landing was completed and some interior header work was finished to mark the 17th day of work on the project. Concrete will be poured on Tuesday or Wednesday, weather permitting. Thanks to Dave and Steve for taking one for the team on a day they could have been kicking back and enjoying the day off. Great effort guys!


Dave Wosika and Steve Clarke setting the first post in place for the landing.


Steve Clarke gives Dave Wosika a hand with the deck planks.


Steve Clarke works on a window header on the first floor.
 


DAY 16: PRESS BOX DOOR & WINDOWS INSTALLED
Press Box Enclosed To Meet Electrical Code, Soffit Work Begins

Tuesday was a busy day for Dave Wosika and John Clare from Stahl Construction sister company Tekton as they finished shingling of the roof, began work on the overhang soffit and fascia and also installed the press box windows and door.


Tekton carpenters John Clare and Dave Wosika finish work on roof


Tekton carpenters John Clare and Dave Wosika work on roof overhang soffit.

Next up is to finish the overhead fascia, install the stairs and finish the exterior siding. Work will continue on Saturday.


A very spacious press box with removable windows for a great view.

The only other exterior work to be completed yet will be the pouring of the outside sidewalks.


East side view showing doors and installed press box windows.
 


DAY 15: ELECTRICAL COMPLETE, ROOFING BEGINS
City Does Rough-In Inspection And Electrical Inspection On Monday

The weather was much more cooperative on Monday as Keith Habeck of ColliSys Electrical wrapped up the interior wiring and was able to pass through the city wiring inspection phase. Habeck also installed a high sodium stair lamp with daylight sensor and also completed wiring for the motion detector security lights. ColliSys is now done until the interior sheet rock is in.


(L-R) Keith Habeck of ColliSys, and John Clare and Dave Wosika of Tekton.

Meanwhile, a Tekton crew of Dave Wosika and John Clare put in work on the roof, completing the roof paper, edging and most of the shingles. Tekton has been the lead labor force, hard at work completing the structure, handling the costly union labor for the project.


The end of day 15 and the roofing and shingles are finally in place.

The Cougars held a small appreciation day ceremony prior to their final home game, thanking those who generously donated to the project.


Stahl representatives Clark Evans and Josh Gangestad in front of new building.
 


DAY 14: BUILDING WRAPPED, SIDING BEGINS
Weather Holds Back Expected Progress, But Much Still Accomplished

Stahl Construction and sister company Tekton Construction combined forces on Saturday for a big hearted volunteer effort to get some extra work in for the South baseball concession stand and press box project. Field superintendent Josh Gangestad was on hand, as well as John Clare, Dave Goetzke, Mike Culbertson, Perry Andrews and Craig Kasa, all pitching in on their own time. Project manager Clark Evans also made a midday visit to check on the project's progress.


John Clare, Josh Gangestad, Perry Andrews, Mike Culbertson and Craig Kasa.

The weather was not the most cooperative for the day. With a start time temperature of just 37 and morning overcast skies, conditions were much harsher than expected. An added 30 mph wind put morning wind chill temperatures in the upper 20s, making the wrapping of the building a much more laborious job than normal.


John Clare, Dave Goetzke, Mike Culbertson, Perry Andrews and Craig Kasa.

The building corners and window trim were added and siding of the structure has officially begun. Work will continue this week.


East side of concession stand and press box.


West side of concession stand and press box.

Thank you to the crews from Stahl Construction and sister company Tekton Construction for volunteering their time and efforts and for giving up their Saturday off. Time and labor costs have become larger than expected, all of which Stahl and Tekton have paid out of their own pockets, so the Saturday volunteer time was greatly appreciated by all involved.
 


DAY 13: TEKTON CLOSES ROOF STRUCTURE
Company Preps One Extra Day Prior To Saturday Push


Tekton dynamic duo of Paul Botko and Dave Wosika.

Tekton Construction was back on Friday to put in some extra work in preparation for a big Saturday push from an all volunteer company crew. The dynamic tag team duo of Paul Botko and Dave Wosika were back on the job finishing the truss rafters and closing the roof. Manager Steve Mayfield was also on site to check the progress of the project and assess Saturday's work load.


Tekton manager Steve Mayfield checks delivery of materials.

Pro-Build boom-truck driver Dan Borck delivered the last major load of materials in the morning, while manager Dan Lieser made a late afternoon call to pick up left-over lumber and drop off the Tyvek wrap for the Saturday work crew.


Concession stand ready for siding and shingles.

Many thanks to all of these fine gentlemen for the wonderful work they've done for Lakeville South high school, District 194, and most especially, South Cougar baseball.
 



DAY 12: PRO-FAB TO DESIGN CUSTOM WINDOWS

Lakeville Metal Fabrication Company To Provide Concession Windows

Pro-Fab Welding & Machine stopped by the site to assess the structure and materials needed to create the custom designed flip-up metal windows. Owner Ben Stuber measured the window openings in anticipation of creation of the custom designed flip-up windows to be featured in the first floor concession stand.

The new facility will utilize metal flip-up windows, very much like those used in the previous Pepsi and Coke concession wagons that the boosters have used in the past. The windows will act as an overhead awning when open to provide shade and also to protect patrons from the rain. They will also provide much more security than standard glass windows. The new custom designed windows will be the last exterior component added to the new concession stand and press box facility.


Pro-Fab Welding & Machine owner Ben Stuber writes down window openings.


DAY 11: COLLISYS WIRES INTERIOR OF BUILDING
ColliSys Gets interior wiring Ready For New Building

ColliSys (Collins Electrical Systems) had the building all to themselves today as they prepared the interior wiring for the new first floor concession stand. Once the wiring is done the insulation and sheet rock will go up, after the city inspects the wiring and the framing of the project.


The first floor concession stand gets wired for juice.

The second floor wiring would have been completed today, but with no roof to escape the heavy afternoon rain that came, the electrical crew had to call it a day early. They will resume the remaining electrical work on Monday.


Keith Habeck and Scott Smith prepare the lower half for the electrical.

Cougar baseball thanks Bret Young and the management crew at ColliSys for their excellent and generous help on the project and for sending in their superb crew of Habeck and Smith.


DAY 10: POWER BACK ON, PRESS BOX ENCLOSED
ColliSys Reroutes Main Power; Tekton Closes In 2nd Story Press Box

A major hurdle was surpassed on Tuesday when ColliSys electricians were able to finally reroute the main transformer and attach it to the new concession stand building, restoring power to the varsity baseball field. Keith Habeck and Scott Smith worked double-duty to get power back on in time for the varsity game at 4:15. They were successful in meeting their deadline as power was restored a full hour before game time. Great work from two outstanding electricians. Way to go Keith and Scott!


ColliSys electricians Keith Habeck and Scott Smith attach main transformer.

Another dynamic duo also had a great day of success as Stahl sister company Tekton had Paul Botko and Dave Wosika work on completing the second floor press box. These two showed why they are both highly regarded and skilled carpenters with an outstanding day on the job. Not only did they finish framing and enclosing the second floor press box, but they also were able to set the truss rafters in place for the roof structure. What a huge day Paul and Dave! Excellent work from two great guys.


Tekton builders Paul Botko and Dave Wosika Work on 2nd floor press box.

Work on the structure will now be completed on Saturday as Stahl and Tekton will send in a larger crew to finish the entire project in one day, just in time for the donators' recognition and appreciation day to be held prior to Monday's last home varsity game. A small ceremony will be held before the South versus Bloomington Kennedy game. Please come out to say thanks for the outstanding contribution from these fine companies.


DAY 9: CONCRETE IS POURED FOR FIRST FLOOR
Apple Valley Ready Mix And Viking Concrete Pour Cement Floor

It was a day for concrete work as Apple Valley Ready-Mix came through once again with a contribution of fresh cement for the concession stand floor. AVR driver Brian Runpza ran the mixer while Viking Concrete & Masonry of Elko did a superb job of managing the "mud." Special thanks to Pete Fischer at AVR for the donation of the much needed concrete. If you have any concrete needs, please give Pete and the good folks at AVR a call to show your appreciation for their great support for Cougar baseball. (click on ad on this page for more info)


Apple Valley Ready-Mix (AVR) feeds cement through an open window.

The Fredrickson brothers were out in force today to handle the concrete from AVR. As always, the crew from Viking Concrete & Masonry of Elko did an outstanding job on the cement pour. Many thanks guys for another job well done. Sidewalks around the building will be next up for the crew very soon.


Luther Schmidt, Brad & Terry Fredrickson and Matt Lyrenmann in the mud.


DAY 8: SECOND FLOOR BEGINS TO TAKE SHAPE
Project Moving Along; Press Box Walls Begin To Go Up

The press box began to take shape on Friday afternoon as Stahl Construction sister company Tekton began raising the second floor walls. Joe Kelly and Jim Spicer will set the press box windows on Tuesday, with roof trusses to follow shortly after.


Jim Spicer and Joe Kelly raise the second floor press box walls.

The second floor framing will not be finished until Tuesday now since Monday is assigned as a concrete day for the pouring of the inside first floor. Work will speed along quickly for week two.


Jim Spicer and Joe Kelly from Stahl Construction setting wall number three.


DAY 7: FIRST FLOOR COVERED; JOISTS IN PLACE
Walls Get Covered In Chipboard; Second Floor Joists In Place

The work progresses on the Cougar baseball concession stand and press box. Day 7 concluded with the sides being finished in chipboard and the second story floor joists installed.


Jim Spicer, Mike Culbertson and Joe Kelly install upper floor joists.

The framing project will continue on Friday, and hopefully have the second floor walls framed and ready for chipboard.


Dan Borck of Pro-Build delivers materials for the second floor and the roof.


DAY 6: STAHL TAKES OVER; FIRST FLOOR IS FRAMED
Stahl Construction Begins Building Phase of First Floor On Wednesday

The long awaited Cougar baseball concession stand and press box project began to take shape today as Stahl Construction came in early to start the framing portion of the project. The crew was able to complete framing of the first floor concession stand today, with minimal setbacks to deal with.


(L-R) Jim Spicer, Mike Culbertson and Joe Kelly begin framing first floor.

Tomorrow the crew will begin work on the framing of the second story press box facility. The structure, when done, will be one of the largest such facilities in the state.


Joe Kelly of Stahl Construction visits with Pro-Build's Dan Lieser on materials.

Many thanks to Stahl Construction for the excellent labor work performed by Joe Kelly, Jim Spicer and Mike Culbertson. Also special thanks to Pro-Build's Dan Lieser for the very generous donation towards materials and their coordination for the project.


DAY 5: FOUNDATION HOLE IS BACKFILLED
Friedges Backfills Surrounding Hole; Structure Is Now Ready To Build


John Friedges (Bobcat) and John Tompkins backfill around foundation.

The final pieces of the concession stand / press box foundation were completed on Monday (5/4) as Friedges Excavating filled in the remaining excavation and surrounding trenches for the block foundation. Dave Peterson completed the city inspection and Friedges quickly filled the remaining holes with the proper fill and then topped with sand in preparation for the concrete flooring.


Foundation is prepped and ready for floor and building of wood structure.

With rain and thunderstorms expected for Tuesday, a Wednesday start by Stahl Construction for framing of the first and second floors will finally begin.


DAY 4: PRESS BOX FOUNDATION SEALED
ColliSys and Stahl Both Work On Sunday To Prep For Monday Backfill


Keith Habeck of ColliSys puts finishing touches on electrical work.

LSHS and ISD 194 are most fortunate to have such dedicated crews that actually work weekends. Sunday was no exception for Stahl Construction and ColliSys electrical systems. Josh Gangestad from Stahl prepped the interior foundation walls with insulation, while Keith Habeck from ColliSys finished off the remaining underground electrical work, all in time for a Monday inspection and then backfill from John Friedges of Friedges Excavation. Also completed was the sealing of the exterior walls to help waterproof the foundation.


The exterior walls have been sealed for waterproofing of the foundation.

The alumni Cougar Baseball Boosters are thrilled to have such a dedicated group involved in helping to bring the dream of a revenue fulfilling concession stand with second story press box to fruition for the baseball program. Thanks very much to Keith and to Josh for the outstanding extra effort on a Sunday. Cougar nation is most certainly indebted for their generous donation of time and labor.

If you or your company should need expert electrical work done for your home or commercial business, please give Keith Habeck and the good folks at ColliSys a call at 763-535-6000. (click on ad on this page)


DAY 3: FOUNDATION IS DONE
Crew Works On Saturday To Complete Foundation Ahead of Schedule


Viking Concrete & Masonry of Elko puts the final touches on the foundation.

Because of their extra weekend effort, the great crew from Viking Concrete & Masonry came in on a Saturday morning and finished off the foundation work for the new concession stand / press box ahead of schedule. The crew of Terry Fredrickson, John Ricci, Doug Swedin and Matt Lyrenmann worked extra hard to finish early so that framing of the new facility could begin on Tuesday from Stahl Construction. The alumni baseball boosters cannot say enough good things about the outstanding quality, professional work and superb effort put forth from Viking Concrete & Masonry of Elko. Thanks guys for a job well done!

If you should ever need concrete and masonry work done, call Terry Fredrickson and Viking Concrete at 952-461-3257.
(click on ad on this page for more info)


Great crew: John Ricci, Terry Fredrickson, Matt Lyrenmann and Doug Swedin.


DAY 2: PRESS BOX FOUNDATION WORK
Footings Poured And Block Foundation Takes Shape For New Building


Terry Fredrickson of Viking Concrete & Masonry working on foundation.

In a day that started at 5:30 for baseball booster Randy Sleeper, the foundation work for the Cougar baseball concession stand began to take shape. Sleeper and his company, Heartland Builders, made the early morning run for the donated block from Anchor Block in North St. Paul. It actually took three trips total, but the crew was able to deliver the much needed block and mortar in time for the masons to begin work. Cougar thanks to Randy Sleeper for the early morning work and numerous trips.

Back at the site, John Friedges came back for a second day to help excavate footings for Terry Fredrickson and the crew from Viking Concrete. The team was able to meet a 9:30 inspection deadline from the city. After that, Fredrickson and crew were able to pour the footings with donated concrete from Pete Fischer at AVR (Apple Valley Ready Mix). It wasn't long before Fredrickson and his crew were laying foundation block at a quick pace, while Keith Habeck from ColliSys put in a second day of routing wires for the project. Most of the foundation work was laid up, but not all work could be finished before the end of the day. Both Habeck and Fredrickson graciously agreed to come back and work on their day off on a Saturday in order to get the foundation work ready for framing of the upper floors by Stahl Construction early next week. That is above and beyond the call of duty and all parties should be commended for their good nature and tireless effort in getting the project done early.

While this is solely an alumni booster project, not being handled by ISD 194 nor LSHS, both Fredrickson and Habeck stayed late in order to do work not on their schedule, all to get electricity for the South vs Rosemount game, even though an already previous understanding was made with the coach that he would more than likely be without power for probably just one varsity game. Keith Habeck had to unexpectedly stay late the first two days in order to do non-booster work for the school, just so the team would not have to go without electricity and a scoreboard. The next day, Terry Fredrickson also stayed late and had to loan his own company generator, even though one could have been pre-arranged from the school. This was clearly above and beyond the job description for both men and their companies, so a very special thanks to both of these men for acquiescing to the unexpected and not sanctioned, non-booster work. Those are two good people that showed the real class and good hearts to meet the un-required tasks placed on them at the end of their hard work days. A very special Cougar thanks to both for being good sports by doing non-booster work. Great job guys for going the extra mile!


DAY 1: PRESS BOX FACILITY FINALLY UNDERWAY
After Almost Two Years, Project Gets Underway On Thursday (4/30)


John Friedges and crew, along with ColliSys electrician Keith Habeck (right).

It's been almost three years in the planning, but the alumni Cougar Baseball Boosters are finally realizing their long standing goal to provide the South baseball program with a valuable revenue tool and needed field amenity at the same time. After many setbacks, the boosters finally broke ground on Thursday (4/30/09) with the beginning of excavation for the concession stand and press box, performed by John Friedges and crew. Working in a light rain, the crew from Friedges Excavating graciously gave of their equipment and own personal time to donate their efforts for the good of Cougar baseball. They are to be commended for their invaluable sacrifice and the alumni boosters cannot thank them enough.

Also involved in the process was ColliSys (Collins Electrical Systems) and Keith Habeck as they rerouted the massive voltage lines that ran directly through the excavation site. Due to a missed electrical line locate from a metro utility locating service, the major electrical trunk line was accidentally cut, making life much harder for Keith Habeck and ColliSys who are also generously donating their time and efforts for the good of Cougar baseball. Mr. Habeck took the setback in good stride and has amiably worked through the unnecessary extra work with a great attitude and understanding demeanor. We thank Keith for his hard work in the trenches. (Literally)


John Friedges operates backhoe as he excavates project site.

If you are in the need of landscaping needs, equipment rental, or excavation work, please help the boosters thank John Friedges by giving them a call at 469-2996. (click on the ad on this page)

A heartfelt Cougar thank you to the crew from Friedges and ColliSys for jumping on the project, literally at the last minute. It is greatly appreciated. A gallery page of the construction process will soon follow.

Thank you again to Friedges Excavating and Collins Electrical Systems. A job well done guys!


STAHL CONSTRUCTION SIGNS ON WITH BOOSTERS
Construction Company Will Supervise Concession Stand Project

After many unfortunate delays in the Cougar Baseball Boosters' concession stand project, the group is happy to formally announce the latest partner in their efforts to build a revenue generating tool for the baseball program. Stahl Construction has agreed to sign on to help with the concession stand / press box facility. Stahl is responsible for many large projects in the city, including the new city hall and many of the schools in town, including our own Lakeville South. The boosters are elated to have the support of Stahl Construction. Thank you guys!


Plan # 3 - two story stick-built facility; concession with press box

A full story has been posted in the upper right column of this page, as well as more on the official Cougar Baseball Boosters' website, detailing the setbacks and the progress made to date.

 Stay tuned to this website for more concession stand info.

Cougar Baseball Concession Stand / Press Box Project


Painted outline shows new concession stand location. (click on picture)


CONCESSION STAND STARTED WITH PROBLEMS
Major Obstacles Lay In The Path of The Baseball Concession Project


Key: Red lines=concession stand, white lines=surrounding sidewalks and patio.

The original baseball concession stand plan put forth by the Cougar Baseball Boosters hit a considerable roadblock early on. More accurately, irrigation water lines in the surrounding grass became an obstacle.

The concession stand was proposed to be built on the north end of the asphalt in the grass, between fields one and two, for easier access to baseball, as well as future soccer events. That plan was scrapped due to the ground limitations. A new site was sought, due to the deeply buried water irrigation lines. Instead of a fall 2007 groundbreaking, the boosters had to put off their plans, actually going back to the drawing board for a new option that would fit their second site option.

Three primary locations were identified, as well as a fourth alternate location. The first primary location and the alternate location were eliminated early on, with sites two and three still available. Of the two remaining, site number two was the most attractive for many reasons, one of which was that the attraction of a press box which could be built on top.

See:  Concessions  |  Press box  |  NEW drawing

A press box was a significant need for the varsity facility, so the boosters explored the option of a two story facility to take care of both needs with one project. A center oriented concession stand behind the backstop would feature open windows on three sides for more customer service availability. It would also serve as a buffer between the home crowd and the visitor crowd, keeping both at a friendly distance. It was a good fit in the end.


The first and fourth options are blocked by water irrigation lines (in red).



 
 

Copyright © 2009 Lakeville Cougar Baseball